Milestone
|
Comments
|
Target
|
Applied
|
Status
|
|
Airport Authority Clearance
|
Pre-requisite
to HUDA Application
|
|
|
APPROVED
|
|
Fire Authority Clearance
|
Pre-requisite
to HUDA Application
|
Jun '09
|
|
Will submit the file around Jun 09
|
|
HUDA Submission
|
Complete/Partial
Application
|
Jul '09
|
|
Will apply either for 5 floors or for the
total height
|
|
MOES
|
Not a prerequisite for HUDA. However,
a required clearance
|
Oct
'09
|
|
Expect to submit in Oct 09 or before
|
|
HUDA Approval
|
Expected
to take 5-6 months
|
Oct
'09
|
|
|
|
Begin Construction
|
Soon
after receiving HUDA Permission
|
Oct 09
|
|
Advertising, Product Launch and
Construction to begin
|
|
Property Handover
|
24 to
30 Months from beginning of construction
|
End '12
|
|
Will start handing over initial set
of bookings
|